Building the New Library 2


May 19 - 20.
The plinth outside the north door of the Abbey Church has been cut away to allow the new connecting cloister to be built.
Foundations for the cloister link to the north door of the Abbey Church.
The base for the main building has been flattened.
Internal drains are in position.
Drainpipes laid along the north wall of the library.
A trench has been dug along the west side,
of the library for drain pipes to be installed.


May 29 End of week 5
The foundations are now complete and shuttering is in place for the concrete base.
The foundations of the cloister link.
The whole site from the north west,
and from the north east.

June 6 End of week 6
The metal work ready to receive concrete
for the floor of the cloister link.
The damp course membrane in position in the cloister.
The damp course membrance for the main block, looking west.
Left Looking north from the north door of the Abbey Church.

Right A silo in place at the edge of the site.


June 20 End of week 8
View of progress from the north west.
From the north door of the church.
From the south west.

June 23
Bricklaying of the outer walls has commenced.

June 24 Mid-Summers Day. The walls continue to grow aided by good weather.